Home Articles From the Editor KPIs for Agile Teams
|
Written by Roger N. Dunn
|
|
Tuesday, 13 May 2008 |
Today's Agile teams contend
with challenges that few development visionaries could have imagined when the
foundations for Agile were first put in place.
In this article, we will examine Key Performance Indicators (KPIs) that
Agile teams can use to achieve transparency into key development processes, and
fulfill the customer requirements of our maturing world.
1.0 - Coming of Age
Agile methods have truly
come of age. The years since Jeff
Sutherland's pioneering work on Scrum in 1993[i], and Kent
Beck's creation of XP in 1996, have proven Agile's enduring qualities.
The world into which Agile
has matured poses a new set of challenges to which Agile must now rise. We've moved from the physical bullpen to the
virtual bullpen, with Agile teams contending with time zones, language barriers,
and cultural distinctions. We've moved
from coding guidelines to strict regulatory compliance. In fact, the development governance
requirements for some industries is so strict that heavier-weight methodologies,
with their emphasis on documentation, contracts and plans, begin to emerge as
more attractive than their lighter-weight counterparts.
In a maturing environment,
being better is not enough. We have to
renew and reinvigorate our commitment to our customers, whether the external
customer who buys our product, or the internal business unit counterpart who we
serve. We have to embrace that same
commitment to our management, the folks who fight for the budget and resources we
need to accomplish our tasks.
A key component to this
commitment is understanding new requirements in three areas: traceability,
auditability, and compliance. It's not
good enough to tout the benefits of Agile, we have to prove those
benefits. And there's no better way than
actively partnering with our customers and management alike, in a way that is
meaningful to them.
2.0 - Process and KPIs
Software projects are
usually evaluated in terms of either process or outcome. Agilists put special focus on process so that
a successful outcome may be achieved, and strike a good balance between team
and customer. But we also recognize that
a process perspective is not, by itself, enough. To make a process really perform, we have to
understand it, characterize it, benchmark it, and optimize it. KPIs are the power tools for accomplishing
this; by using KPIs, we're able to enhance processes to superior outcomes.
Process distills to three
basic elements: incoming materials, outgoing product, and the steps by which
labor transforms one into the other. KPIs
are there for us at every step of the way.
They describe the quality of incoming and outgoing materials, the
stability of the transformational steps, and the overall capability of the
process to perform at expected levels.
We can learn from the
parallels between Agile's coming of age and manufacturing. Industrial engineers began the formal study
of process and KPIs in the 1950s. Over
time, competition and tightening margins drove efficiency, often coupled with
regulatory requirements around quality and safety. This resulted in manufacturers squeezing
greater performance out of their processes, while at the same time being able
to retain and audit what was done. Quality
philosophy became increasingly refined, with tools to match. Inspection gave rise to statistical process
control, which in turn empowered today's ultra-high-efficiency lean
manufacturing environments. Because
manufacturers invest in processes, applying KPIs to advances in assembly and
materials technologies, the rest of us get to enjoy the high quality, high
yield, short run, low cost consumer products they produce.
We can apply
manufacturing's three key lessons to development iterations. First, if you are engaged in a process - any
process - there are KPIs to tell you about the quality of the work products,
and the profile of the process that produced them. Second, KPIs gain relevance and timeliness
when they are automated. Third,
mediating process transparency through KPIs enhances communication with
management, suppliers, and customers.
3.0 - Timebox your KPIs
An Agile process transforms
backlog into working software through transformational stages: design,
programming, build and test. In a given
timebox or sprint, the process is characterized by two principals measures: the
volatility, or degree of churn, created by the team with respect to logic
artifacts, such as code and test script; and the volume of the logic artifacts
produced, such as the net number of source lines of code added, or the number
of backlog work items addressed in that timebox. The quality of the work product as it moves
through the process is given by assessing compliance with the team's
engineering standards.
3.1 - Volatility
Volatility informs the team
of the transactions taking place in the process. Visualizing process volatility from a variety
of perspectives brings transparency, and permits lean development governance[ii]. Consider how much we can learn from the
following graph, showing the churn associated with coding changes for a May
2007 timebox[iii],
expressed as gross LOC changed per week for summary activities:
In general, we want to see
coding changes calm down in advance of a release, to give sufficient time for
final test (e.g. integration, acceptance, or production trial). Volatility graphs depict durations and
magnitudes: "Backend Integration" completed in the second week, with modest
code changes (1,300 LOC) relative to the other summary activities. "Web Service Impl" ramped up to a peak period
in the third week; this is a desirable trajectory in a timebox, often likened
to an aircraft flight, with a smooth glide plane to land at the code freeze
date. "Client Features", on the other
hand, is undergoing such a high rate of change in the final week that it is
clear that extra scrutiny will need to be given to contain the risk introduced
to the project by those late breaking changes.
The next example shows how
churn can also be examined in terms of who is contributing to the code base
through the course of the timebox. This
yields two valuable aspects of process: are programmers able to complete tasks
in a timely manner, and is anybody making unauthorized changes to our project:
Contribution is not the
same as productivity: there are many factors to programmer productivity beyond
how many lines we code. However, if
developers are unable to contribute work against backlog in a timely manner,
then either they are blocked and need assistance (e.g. Barney seems to have
gotten blocked before the halfway point), or the breakdown of coding tasks may
be too coarse grained for real agility.
Visualizing contribution support Agile methods by letting us put course
corrections and mentoring in place early on, when they can do the most good.
There are many other forms
of volatility analysis that yield insight into process: by stream (or branch);
by framework; by type of logic artifact, to name a few. The important thing is to start with a small
set of simple, pragmatic measures that make a difference, and build from there
over time.
3.2 - Volume
The volume KPI expresses
the changing size of the logic artifacts over time. There are many uses for this KPI: volume is
one of the principal correlations to future maintenance costs; OO efforts often
want to see a reduction in volume at various stages, as classes are refactored,
combined and collapsed; volume is fundamental to code coverage and defect
density; and more.
The following example shows
the net change in the volume of the different sort of logic artifacts undergoing
change in our May 2007 sprint. In this
case, we have a steady increase over time in the java, xml, and other sorts of
things that make up the project:
When we begin to visualize
volume changes, we become better tuned to process capabilities. How many developers does it take to review
12,000 net new LOC? Given prior defect
density and the "law of large numbers", what can we expect in terms of new bugs
found and not found in this new code?
How many developers and which skills will it take to maintain
institutional memory of this code for future maintenance efforts?
3.3 - Quality of Work Product
The essence of development
governance is to assess the compliance of the work product against engineering
standards. If you don't have standards,
you have no basis for a quality program.
If you have standards and no compliance assessment, you can't know where
you stand with your quality program. The
work product quality KPI opens the window into the process so that you can
achieve real development governance.
Most teams have standards,
and they usually include coding guidelines, compatibility with language vendor
guidelines and industry standards, and keeping a handle on code
complexity. Here's the trend in the
injection of complexity in our May 2007 sprint:
The graph shows the average
complexity and range bars (min and max) for Java code changed each week. The team standard was to contain complexity
to 10 or lower; we can see that the team complied with that standard, never exceeding
6. In other sprints, an uptick in
complexity prompted peer review, enhanced unit testing to ensure coverage for
the new execution paths, and even rework to re-express the logic in clearer,
more maintainable terms.
4.0 - Tools and Automation
Change management tools can
offer a platform for deriving the KPIs described above. Your ability to visualize capabilities is
predicated on tool capabilities. The
examples given here are all based on IBM Rational ClearCase UCM. Other examples of change management well
suited both for Agile teams and deriving KPIs include AccuRev, Perforce,
Subversion, and Rational Team Concert / Jazz.
Automation helps you get
traction with KPIs by delivering timely reports without adding administrative
burden to the team. Vendors like
SourceIQ offer solutions that integrate with your existing change management
infrastructure to automate the derivation and syndication of KPIs.
As you seek to apply KPIs,
consider your process capabilities, engineering standards, and tooling together. You'll find a treasure trove of KPIs ready to
be explored, baselined and shared. This
empowers teams to achieve superior results and demonstrable compliance, even in
a virtual bullpen. Transparency helps
management and customers to understand the value of Agile in meeting their
requirements.
About the Author
Roger N. Dunn is the founder and CEO of SourceIQ, Inc., an Advanced IBM Business Partner focusing on delivering metrics for Agile teams, management and executives. He has twenty-five years' experience leading teams in ISV and IT software development projects. You can reach him at
This email address is being protected from spam bots, you need Javascript enabled to view it
, or visit www.sourceiq.com.
[i]
"Agile Development: Lessons Learned from the First Scrum", Dr. Jeff Sutherland,
http://jeffsutherland.com/scrum/FirstScrum2004.pdf
[ii]
"Lean Development Governance Whitepaper", Scott Ambler and Per Kroll, http://www.agilejournal.com/content/view/768/112/
[iii]
All examples given are based on SourceIQ Enterprise Server analysis of a
production IBM Rational ClearCase UCM environment. Where appropriate, names have been altered to
protect privacy.