Merging Waterfall and Agile Across the Seven Seas |
|
|
|
|
Written by Daryl Kulak and Harish Gopalani
|
|
Sunday, 08 June 2008 |
This article is a story about how an onsite/offshore team
delivered a fixed-bid project using Agile practices. The delivery effort was
very successful. This article highlights our approach, challenges and successes.
Gingerly Steering Away From Waterfall Toward Agile
In early 1990s a consulting practice at our company was
created that specialized in delivering large fix-bid retirement administration
systems. This practice delivered systems using a custom waterfall approach
wherein requirements, design, development, testing & rollout phases were
executed sequentially. The client spent significant time early in the project
and then would finally see the system after the project had spent over 70% of
its resources. While it varied from project to project, the group generally
delivered systems in two releases, the first one approximately 18 months into
the project and the second one 12 months later. In our situation, the team was
experiencing delivery challenges and had incurred significant variances on the
first release. Our leadership (client & consulting firm) was unhappy and
losing confidence. The project delivery executive determined it was time to do
something different. He proposed changing our delivery script and moving things
earlier in the lifecycle.
Our Practice Executives Weigh In
Once our practice executives found about our intent to do
iterative/incremental development, they hit the panic button. The practice had
tried similar approaches before, but thought of it as a laboratory experiment.
They had a number of fires burning and little appetite for something different.
They hit us with a barrage of questions:
l "You have a large offshore
component (approx. 60%). How do you plan on managing work iteratively with
them?"
l"This is a fixed-bid project,
what part of it don't you understand"
l "Fixed-bid projects need to
have signed-off requirements and firm scope, and iterative approaches don't
apply, do they?"
l "When and how will you
baseline scope?"
All great questions! We knew this approach would work, since
we had seen similar things work at a dotcom venture, but we recognized this was
lot bigger and complex (approx. 65,000 hrs of effort). We could articulate some
things but did not have all the answers. We knew we had to adapt. Fortunately
for us, our project delivery executive led the way and posed the questions back
to the group saying, "What other options do we have?" He reflected that
something had to change or else the end result would be similar to previous delays
and cost overruns. After more discussions it came down to the practice
executives staring us down and saying "Okay, in that case you will have to make
this work and you are accountable for the outcome." We were not quite sure if
this was a vote of confidence or a threat, but we believed in this approach a
lot more than waterfall.
Our First Move
One of the most valuable recommendations our delivery
executive provided was for us to visit the offshore team. We had two offshore
centers in Chennai and Bangalore. For this one week orientation/kick
off, we got both teams in Chennai and instead of focusing on technical and
functional orientation (which had been the norm until then), we used Lego toys,
tennis balls and tinker toys to play games that focused on creativity and
innovation. The group had a blast! We then discussed the new
iterative/incremental approach.The team seemed open minded. We followed up with
detail sessions with team leads who ultimately were going to lead them on the
new path and be our eyes and ears 8000 miles away. This was a very different
approach than what this group had been used to. They had been used to taking
orders and the thought that they could now help drive delivery was respectful
and empowering (we found out later that other offsite teams started pleading
for a similar kind of interaction). All this and a lot more was now going to
change.
Experimenting with Agile Practices
We had a lot of constraints. We had a team of 25+ people
(onsite plus offsite) and while this was a great team with lots of smart
people, the group did not have iterative / incremental background. We had to
play coach and mentor. We knew we had to adapt and the best thing to do given
the situation was to use a hybrid methodology approach. The Agile practices we
leveraged included:
-
Time-boxed iterative development - We broke our
delivery into six iterations, each six weeks long. These iterations contained
requirements (typically one iteration ahead), design, development and testing
activities. At the end of six weeks, the code was delivered into a user test
environment. Our users were now able to play with the system and provide
feedback as early as 4 months into the project. (This typically would not have
happened until 10 months into the project.)
We had succeeded in moving things earlier in the lifecycle. We would
have preferred shorter iterations. This was an adjustment we felt we had to
make given the team's lack of experience and the distributed nature of our
development. Even if we wanted to deploy iterations in production, we could not
have done it since the first release of our software (being done by a separate
team) wasn't ready to go live.
-
Lean management, self contained and empowered
teams - The team was split into three functional teams, with some onsite and
offsite component. The onsite team provided requirements, training and
management leadership while the offsite team provided design, development, and
testing leadership. For the first time, offshore teams were now empowered to plan
their own assignments. In the past, this typically was decided by an onsite
manager. The three offsite functional teams reviewed the use case catalog and
identified components to be designed / built / tested within iteration.
Components that were not completed at the end of the iteration moved into the
next iteration. The offshore team had greater control of their destiny, and was
able to make necessary adjustments at the right time. This gave the team a
feeling of having ‘skin in the game' and increased accountability.
-
Scrums - Given our distributed delivery
environment, we used two streams of Scrum. The first one focused on all onsite
team members. We had two onsite centers: Columbus,
Ohio and Santa
Fe, New Mexico. For
many months we held teleconference meetings every business day at 7:00 pm
EST. Our goal was to over communicate in
the beginning and then tone down subsequently. The 15 minute teleconference
call focused on "What issues are holding you back?", "What have you
accomplished today" and "What are you planning to do tomorrow?" Respecting
people's time, we stuck to our 15 minute commitment. The expectation was for
the team members to hang-up after 15 minutes and that if we could not manage a
15 minute Scrum on a daily basis then how could we possibly manage six week
iterations? We must say, except for handful of situations where we sought
team's approval to extend the 15 minute meeting, by far a vast majority of our
meetings got done in 15 minutes or less. The second Scrum stream focused on interaction
between onsite and offsite members of functional teams. We were very ambitious
in our thinking that these would be daily and structured, but then weeks into
the project, given the time zone differences they morphed into 2-4 meetings a
week and became more detailed information exchange sessions. We were successful
in applying the Scrum concept to distributed onsite teams but these took a
different shape for the onsite and offsite team interaction.
-
Detailed velocity measurement - In the spirit of
trust but verify the project
leveraged detailed development velocity metrics to report progress. This metric
was updated weekly and reported on actual development progress versus planned
progress. The metric used iteration plans created by offshore team and reported
progress and calculated schedule deviation on a weekly basis. Using a fast
paced iterative / incremental approach put a higher onus on control metrics.
The rigor applied in planning and reporting was much deeper and, contrary to conventional
wisdom, more rigorous than traditional waterfall development tracking. Not only
did we track features developed, tested, delivered, and components developed,
tested, delivered, but we also were constantly juggling resources to maximize
iteration throughput. This focus on delivering maximum functionality each
iteration helped the team stay on top of their game right from the very
beginning versus the old waterfall approach where things often start slow and
then pick up as phase deadlines near.
-
Continuous Integration and Automated Regression
Testing - This practice probably provided us the biggest bang for our buck.
Code that was developed from multiple locations was checked into a single
repository and a build was generated every night. We used a rookie (fresh graduate
with no business background) to develop automated regression testing scripts.
We started slowly (as iterations progressed), creating a suite of test scripts
that validated key functionality to ensure that the build was functional. This
practice saved us from putting bad broken code in front of the client and
helped develop trust! We truly started living up to their expectations.
-
Paired Programming - While financially it's a
lot easier to implement paired programming offshore than onsite, we did not do
this all the time. We cherry-picked assignments that were more complex and had
higher impact and assigned paired teams. We particularly remember one complex
component where we were able to develop with very high quality in 1/3 of the
scheduled time. This had never happened before. Over a period of time this
turned out to be a great blessing as the job market in India was sizzling hot. Developers
acquired good skills and then flipped jobs for a 25% pay raise. Our paired
programming approach helped retain some of our background and experience. If we
had to do this over, we probably would have had a higher percentage of paired
programming (but still not do the whole project that way). Our experience is
that not all team members are crazy about this approach, this is a team sport
and ‘super stars' and ‘MVPs' do not fit well.
- Retrospectives from iteration - Given the
newness of the approach; we periodically sought input during iterations and
again at the end of the iterations to collect and apply lessons learned.It
helped us identify not only micro level process and resource adjustment
opportunities but also macro level dynamics and motivators that then helped
influence a new delivery culture. Moving things early in the lifecycle forced
issues and failures earlier on and helped us fine-tune and adapt while we still
had time to recover. Our lessons learned ranged from: identifying true
productivity rates, getting a much better feel for our resource capabilities,
understanding our bottlenecks, etc. Perhaps the best thing it did was to
provide the team a sense of purpose, an opportunity to make a difference and an
incredible team experience that years later some of us still have very fond
memories of.
-
Test driven development - Our development team
was required to create unit test plans prior to starting development. This was
a new concept to the team members, who would rather have jumped into coding.
While the offsite development leads oversaw the process, the onsite team had
visibility into the repository where all work products were saved. The
developers reviewed the use cases/design and created unit test plans that were
reviewed by their leads prior to starting development. This was especially
beneficial for junior developers who had little business background.
In summary, while technologies and processes have improved
significantly since 2002, the above experiences reflect adaptations of a larger
Agile philosophy to a specific project instance. And while some schools of
thought may posit that Agile should only be applied in its entirety, we think
teams have the potential to realize delivery efficiencies by implementing a
subset of Agile tenets that are prudent and relevant. We leave it to you to
judge our Agile maturity. The key, we believe, lies in solving business problems
using the best possible tools for your individual situation. In our story, our
release was a resounding success. We delivered a great quality solution within
aggressive timelines and budgets. Our Agile story may be different then your
Agile story and we think that's fine, or as Thomas Harris would say, I'm OK -
You're OK.
About the Authors
Harish Gopalani is a
PMP with over 18 years of application development background and holds a degree
in Mechanical Engineering. He currently works with Nationwide Insurance and has
diverse implementation experience which ranges from developing mainframe,
client server and J2EE solutions and implementing products such as SAP and
CODA. Harish is based in Columbus,
Ohio and can be contacted at
This e-mail address is being protected from spam bots, you need JavaScript enabled to view it
Daryl Kulak is a speaker,
consultant and author with Perficient, Inc (htttp://www.perficient.com), a
NASDAQ-listed IT consulting firm. He co-authored "Use Cases: Requirements in
Context" (Addison Wesley, 2000/2003). Currently,he is co-authoring "Agile +
Rigor: How to Fit Iterations into Large Organizations," due out in 2009. Daryl
is based in Columbus, Ohio and can be contacted at