Written by Sean Sheehan
|
|
Sunday, 07 September 2008 |
Software systems are being delivered to our customers at an
ever-increasing rate. How can we keep up with the pace whilst still maintaining
the quality of our code? I will demonstrate over a series of three articles how
by focusing on the customer throughout our delivery cycle we can deliver
reliable working software with confidence, reduce the number of defects, reduce
our delivery timescales and ultimately save money. You may think this is
nothing new, and that agile development has long since answered this question.
However, even in the agile world there are loopholes which allow us to
bypass the customer. Leading us to deliver what we think they want, rather than
what they were expecting.
PART ONE
Introduction
Writing shippable code is a
daunting task. Ask yourself "Will my customers really be happy?" It's impossible to
predict with certainty that a complex system with thousands of lines of code is
going to be defect free
enough for our customers to be happy. It's true, we know it's never defect
free so we compromise with defect free enough. Our prediction is often based
around the number of lines of code we have touched or written, the number
of defects we have found historically per hundred lines of code and the average
time it usually takes for us to fix a defect. This allows us to
project and track against a find fix curve showing how after 100% code complete
we are stabilising our system. We rely on prediction because of the
uncertainty that is introduced throughout our development cycle by the circles
of information hand-offs and the honest fact that we know we will produce a system which genuinely does have
defects.
What if we could remove, dare I
say eliminate,
the ambiguity and reliance on prediction right from the off? What if we could produce with
confidence shippable code? An impossible task? Several techniques
used within agile software development (Test Driven Requirements, Test
Driven Development, Coding by Assumption for example) can improve our
confidence and quality of our code are still rarely used by many
organisations.
Going on a Journey
Software systems are becoming
more and more complex, though to our customers they have to appear to be
becoming simpler and simpler. People are so much more aware of the time they
spend immersed in our system especially in a day where every click counts. They demand to have
simplicity whilst still interacting under the hood with ever changing technology, standards and
protocols. Yet, we are still expected to keep up with their expectations,
deliver on time, stay within budget and have a robust defect free system.
It used to be acceptable when applications
failed or got stuck every once in a while but those days are long gone. How can
we improve the system we produce so that it genuinely does what it is supposed
to do without failing?
Imagine I'm going on a journey
to somewhere I have never been to before. I'm going to take my family on a day
out and we intend to have a lot of fun when we get there. My wife's expectation
is that we will leave with enough time so that we can enjoy a full day, whilst
still being able to get home at a reasonable hour to get the kids to bed. What
do we do? It used to be that we just pick up a map, try to find where we are
going to and mark out our route following the major roads. We'd guess as
to how long it takes to get there based on our own personal experiences and suggest
a set off and return time - job done. Though for me at least I would state that
most places ended up taking 2 hours to get to, wherever the destination. In
actual fact it takes longer, we end up getting there late, leave early and
don't get what we wanted out of the day.
These days we go to our favourite internet
mapping system. Key in our start and end points, the time we wish to leave,
maybe adjust the route on screen to avoid certain roads and we get a very
detailed plan showing exactly how long each stretch of road is, the time it
should take to travel along on and our accumulative time spent on the journey
so far. No arguments about the route or the time (strangely though 2 hours
journey time, but I keep quiet). What's interesting is our behaviour on the
journey. My wife tells me to take the next left, which should be in about 3
minutes time and that it's just under 1/2 km away. As I turn left, we both say
"that didn't take 3 minutes". We continue doing this throughout the
journey until we arrive at our destination on time and have a great day out.
The route plan has set our expectations
for each section of the plan. We test these expectations at regular intervals
to give us confidence in the plan and to make sure that we are going to reach
our destination as expected. Located at the bottom of the route plan is a
suggestion that there may be inaccuracies along the way. If we are able to
identify them we can provide feedback online when we return home, improving
future route plans for other people.
Our instinctive behaviour is to test our
assumptions regularly and to make corrective actions when these assumptions are
not being met. If the plan isn't clear enough and we keep making mistakes we
might abandon the plan and start following our noses in the vain attempt to get
there on time. We also like to learn from our mistakes, which leads us to
reflect on the journey once we return to see how we can have a better
experience next time.
Having the route plan indicate that there
might be defects is clear admission from the provider that not only was the
plan generated by the information it had at hand, but that there will be allowable defects from time to time.
This also changes our behaviour. It suggests to us that defect free enough is ok, and we go along with it. We even feel
really good when we find a mistake and can't wait to let the route provider
know. We stay loyal to the suggested route just in case we find another one. We
are being the good citizen and fixing the world for everyone else.
Developing a complex software
system is like going on a journey but with a fundamental difference. We know
our start point however our final destination is unclear. We know roughly the
direction we should be heading (or at least we think we know). But we
constantly make adjustments to our journey as we go.
Traditional software development
methodologies tell us to plan, plan, plan,
and then when we are done plan some more. By this I mean produce project plans
showing how we detail all of our requirements, produce comprehensive
design, transfer the design into code, test our system, stabilise our system of
defects and then release to our customer. We follow this plan relentlessly
until we are either done or realise that we need to re-plan and re-adjust our
timescales (the later is the most likely). But it was the detailed journey plan
for our day out which was most successful. This goes against the grain for
agile software development. Or does it?
The Agile journey
Agile
software development teaches us to produce our system by delivering value
to the customer through small increments of potentially shippable code. After
each iteration we reflect on how we worked and make adjustments to improve (Do,
Inspect & Adapt). We plan our journey using the product backlog, but we
only get to the detail in an iteration for the elements we have identified need
to be worked at that time.
For this journey, it's like using a GPS
system in our car. We know where we need to get to, but the GPS is constantly
recalculating our route and our progress. It knows that if a road takes longer
to travel than expected it will adjust our end time. Also if we choose to
deviate from our route (like finding somewhere to eat along the way in a town
we are passing) it will suggest we make u-turns until it recalculates a new
route from our current position. Newer GPS route systems will even keep an eye
out for hidden problems (road works, traffic jams and accidents) again
recalculating our route if these are encountered. It's constantly testing
its own assumptions (as well are we) to ensure that we have a trouble free journey
and arrive safely at our destination. This is something we are not very good at
doing when developing our software system. For traditional software development
models our assumption test is towards the end of the life-cycle while with
agile software development we bring that closer to the code being written
through automated testing. We incrementally derive our requirements through
user stories / use cases then rely on our automated tests to validate if our
code meets our assumptions. This is a huge improvement over testing late in the
cycle. Better still, how about testing our assumptions of our requirements
prior to any system design or code being produced by expressing them as a
series of tests. Enter the world of Test Driven Requirements.
Are we there yet?
Let's explore first
how we know if we have reached our destination: For a car journey
it's quite simple in that we have arrived and stopped the car. In software
though it's a different story. We think we are done when all our features are
implemented, tested and that we have stabilised our defect find rate to a level
we expect would be acceptable by our customers. However, due to the complex
nature of the system we have produced and the project timescales, we know that
there are certain combinations which have either not been exercised or not
exercised enough. We stress test key paths through our system but knowingly
omit large sections.
An extremist would state that when there
are no defects in our system we are done. Since we know in our heart of hearts
that there will be some defects and that our timescales will not permit a
completely defect free system we compromise with defect free-enough. We soften
the blow of this message by producing find / fix projections. We even set
targets against milestones on our project plan. Find / Fix curves are
calculated by estimating how many lines of code we will touch or introduce, how
many defects per 100 lines of code there will be, how long it generally takes
for us to fix a defect and projecting this information on a graph. Our targets
are set against a launch criterion of reliability which is rarely zero defects.
It's this thinking which allows us as a delivery team to become complacent
about bugs in our system. At the end of each iteration we kid ourselves by
announcing that we are done. We demonstrate the functionality we have added and
hide the fact that there are certain scenarios which will cause problems. We
say that we have tested within the iteration when actually a good deal more
testing is required. We pat ourselves on the back with a job well done and
shelve what's remaining allowing us to focus on the next iteration. We told
ourselves that we are done, but we know that we are not completely done.
Changing to the mind set
of completely done is not easy. In most circles people think that this only
applies to the software developers. Managers find it easy to ask "are we
done yet" but fail to realise they are also a part of this message. They
should be able to see clearly and be part of the progress without asking and
have confidence in what they see, after all our GPS route system constantly
informs us with elapsed journey time and estimated arrival time displayed on
it's screen all the while through our journey. We never stop, get out our calculator
and double check the numbers, we trust what we see. The information radiates
out to us and we are kept warm in the knowledge that all is fine.
Knowing that we are completely
done requires one key piece of information, our criteria for a successful outcome. If we
do not know this then we cannot even claim that we are done. This doesn't just
mean that there are no defects in the code, or that we haven't broken existing
features, it means that the features are also fully satisfying the needs of the
customer. Even if we do express our requirements as user stories or use
cases we often fail to provide acceptance criteria. If we did then we
would know for each requirement whether we were able to achieve a successful
outcome. Continuous automated testing against these outcomes would then start
to show us how far we had come, and how far there was to go just like the GPS
route system without the reliance on prediction models.
Part two of this article will focus on our
criteria for a successful outcome, how we express this in the context of
software and will uncover the loophole many agile teams overlook. Part three
will then demonstrate how this can overcome and transferred into our code so
that we can deliver shippable code.
About the Author
Sean Sheehan is a lean software transformation
manager for a leading embedded control systems company which he has been with
for nearly 10 years. A master black belt candidate for software design for six
sigma, certified lean six sigma black belt and certified ScrumMaster with over
20 years software development experience in embedded c++. Sean is currently
assisting lean software / agile transformation within his current division
helping transform three groups from different time zones in applying these
techniques collectively. You may link with him at http://www.linkedin.com/in/spjsheehan.